| June 1904, No. 76 | The Railway and Shipping World (Toronto) | Page 187, col. 3 |
Railway development.
Projected lines, surveys, construction, betterments, etc.
...
Lindsay, Bobcaygeon and Pontypool Ry.—Tracklaying was commenced towards the end of May, and is expected to be completed in June. Grading in Lindsay, to the station and yard, was completed early in May, and work on the sidings, 2,700 ft. in length, was then gone on with. Station buildings at Lindsay and Nestleton, a water tank, five miles north of Burketon, were about completed, and the decking of the bridge across the East Creek, about five miles south of Lindsay, had been completed. It is expected to have the line completed ready for operation by July 31. (Feb., pg. 61.)
Railways: L.B. & P.Ry.