Grand Trunk betterments, etc.
...
Brantford deviation.—The earthwork on the Lynden-Brantford cut-off was expected to be completed towards the end of May, when tracklaying would be commenced by the company. The grade is 18 ft. wide where the fill is less than 6 ft., and 20 ft. wide where it is over 6 ft. J. A. Dart was the contractor for the earthwork.
In connection with this deviation considerable work is in progress in Brantford, including the lowering of the tracks of the Tillsonburg-Harrisburg branch on St. Clarence St.
A number of officials were in Brantford May 10, looking into the question of the new station which it is proposed to erect on an early date on the site of the present building. (May, pg. 177.)
Railways: G.T.Ry.