Portland terminals.—J. E. Dalrymple, assistant to the General Manager of the Grand Trunk, on returning recently from Portland, Me., said satisfactory progress is being made with the new wharf and elevator. Over half the wharf is completed and the flooring laid. The rocky formation of the site where the excavations had to be made for the new elevator delayed the foundation work for the elevator. Hardwood piles with steel points had to be used to sink into the rock. The foundation is nearly finished, and along one side the cement pillars have been constructed.