Canadian National Railways construction, betterments, etc.
...
Kashabowie Subdivision line revision.—Tenders were received recently for the construction of a line revision between miles 32 and 35.65, Kashabowie Subdivision, Ont. We are officially advised that this revision will provide a second main line, with improved gradients of 0.5%, which will form a part of the double track line which will eventually be built between the point of connection now under construction between the Graham and Kashabowie Subdivisions and Port Arthur. The material involved in the grading consists of rock, loose rock and common excavation—rock predominating. The construction will be C.N.R. main line standard ; culverts, reinforced concrete boxes, or reinforced concrete pipes. The work is to be completed by Dec. 31.